DRAFT - April 7, 2004 - DRAFT
Federal Guidance on the Use
of Off-Site and Out-of-Kind
Compensatory Mitigation
Under Section 404 of the
Clean Water Act
I. Purpose
This document provides interagency guidance on the use
of off-site and out-of-kind compensatory mitigation undertaken to meet
permit requirements under Section 404 of the Clean Water Act (CWA). The
permit program relies on compensatory mitigation to offset unavoidable
impacts to aquatic systems by replacing aquatic functions lost in association
with permitted activities.
For the purposes of this document the relevant terms are
identified as follows:
On-Site: within the project boundaries and/or
areas adjacent or contiguous to the impact area (1)
Off-Site: areas not meeting the definition for on-site
In-Kind: the same physical and functional type as that of the
impact area (e.g., same Cowardin
Subclass or hydrogeomorphic type)
Out-of-Kind: a different physical and functional type than the
impact area (2)
II. Operational Background
CWA Section 404 regulates the discharge of dredged or fill
material into waters of the United States, including wetlands. The Army
Corps of Engineers (Corps) is responsible for processing Section 404 permits
and analyzing impacts associated with proposed projects that include the
discharge of dredged or fill material into jurisdictional waters. Under
40 CFR 230, the Corps reviews proposals using a "sequencing"
procedure: avoidance, minimization and finally compensation for unavoidable
impacts. When an applicant proposes a project with unavoidable impacts,
the Corps often requires the applicant to provide compensatory mitigation.
The mitigation package can include different types of mitigation, including
both on-site and off-site mitigation, or in-kind and out-of-kind mitigation.
However, provision of the mitigation package is the responsibility of
the applicant (33 CFR 320 et seq.).
The Corps reviews and approves the proposed mitigation
plan in accordance with EPA regulations (40 CFR Part 230). In most cases,
the applicant provides the Corps with one mitigation plan for review.
The Corps' decision to accept on-site or off-site, in-kind or out-of-kind
mitigation is based on a review of the applicant's proposed mitigation
plan, not on a comparison of several mitigation sites. The Corps will
review the applicant's mitigation plan and determine if the proposal meets
regulatory requirements or must be modified (which can include changes
to the plan, additions, or reductions in specific types of mitigation).
In making a determination that a proposed plan is acceptable, the Corps
must consider not only the environmental factors, but practicability (3)
factors as well (33 CFR 320 et seq.; 40 CFR 230 et seq.).
III. Existing Policy and Guidance
There are several documents that currently provide guidance
on compensatory mitigation for the 404 Permit Program and they are discussed
in this section. The Section 404(b)(1) Guidelines of the CWA are regulations
that govern the evaluation of permit applications. Other documents provide
guidance concerning the use of on-site and off-site, in-kind and out-of-kind
compensatory mitigation:
- The 1990 Memorandum of Agreement concerning the Determination
of Mitigation under the Clean Water Act Section 404(b)(1) Guidelines
(Mitigation MOA) between the Environmental Protection Agency (EPA) and
the Department of Army;
- The 1995 Federal Guidance for the Establishment, Use
and Operation of Mitigation Banks (Banking Guidance);
- The 2000 Federal Guidance on the Use of In-Lieu-Fee
Arrangements for Compensatory Mitigation under Section 404 of the Clean
Water Act and Section 10 of the Rivers and Harbors Act (ILF Guidance);
- The 2002 Corps Regulatory Guidance Letter (RGL) 02-2,
Guidance on Compensatory Mitigation Projects for Aquatic Resource Impacts
Under the Corps Regulatory Program Pursuant to Section 404 of the Clean
Water Act and Section 10 of the Rivers and Harbors Act of 1899. (4)
A. Section 404(b)(1) Guidelines (The Guidelines)
The Section 404(b)(1) Guidelines require that impacts be
avoided if there is a practicable alternative to the discharge that would
have less adverse impact (40 CFR 230.10 (a)). The Guidelines also require
that appropriate and practicable steps be taken to minimize unavoidable
adverse effects (40 CFR 230.10(d)). Compensatory mitigation may be used
to minimize potential adverse effects (40 CFR 230.75(d)) to the aquatic
environment (5).
Subsequent documents, discussed in the following sections, provide further
clarification regarding mitigation requirements established in the Guidelines.
B. Existing Federal Guidance concerning Off-site Compensatory
Mitigation
The 1990 Mitigation MOA emphasizes the agencies’
preference for compensatory mitigation to be undertaken, when practicable,
in areas adjacent or contiguous to the impact area (on-site compensatory
mitigation) (6).
This preference was expressed because some aquatic habitat functions that
depend on location and environment may not be transferable to another
location - functions such as flood control, nutrient retention, sediment
filtering, and critical habitat for endangered or migratory species, to
name but a few. The Mitigation MOA further states that in cases where
completing all compensatory mitigation on-site is not practicable, off-site
compensatory mitigation "should be undertaken in the same geographic
area if practicable (i.e., in close proximity to and, to the extent possible,
the same watershed)."
More recent guidance on mitigation banks and in-lieu-fee
mitigation also address on-site vs off-site mitigation. Mitigation banks
are an appropriate way to satisfy compensatory mitigation requirements
off-site when 1) on-site compensation is not practicable, or 2) use of
the mitigation bank is environmentally preferable to on-site compensation.
In-lieu-fee arrangements are another option for satisfying compensatory
mitigation requirements off-site. Both the Banking Guidance and the ILF
Guidance recognize that for minor impacts (such as those typically authorized
under General Permits), off-site mitigation is often preferable because
under a Mitigation Bank or ILF arrangement, a number of small mitigation
requirements can be consolidated into a larger project with a better chance
of ecological success than numerous scattered projects.
Additionally, RGL 02-2 briefly discusses on-site and off-site
mitigation. RGL 02-2 states that mitigation should be required, when practicable,
in areas adjacent or contiguous to the project impact site. However, off-site
mitigation may be used when there is no practicable opportunity for on-site
mitigation, or when off-site mitigation provides more watershed benefits
than on-site mitigation.
To summarize, the documents discussed above note that when
conditions required for successful on-site mitigation are present, on-site
mitigation is generally preferred because it provides compensation for
functions that are lost or degraded at the impact site. However, there
are circumstances in which on-site mitigation is not practicable nor is
it environmentally preferable: e.g., minor impacts associated with general
permits, or compensation for larger impacts that, if mitigated on-site,
would be surrounded by urban features and prone to anthropomorphic impacts.
Under such circumstances, the appropriate use of other environmentally
preferable compensatory mitigation alternatives such as off-site mitigation,
use of a mitigation bank, or use of an in-lieu-fee arrangement should
be evaluated. RGL 02-2 states that when evaluating compensatory mitigation
options, Corps Districts will consider 1) the likelihood for ecological
success; 2) ecological sustainability; 3) practicability of monitoring
and maintenance; 4) proximity to watershed where related impacts occur;
and, 5) the economic costs of alternatives when deciding between on-site
and off-site mitigation.
C. Existing Federal Guidance concerning Out-of-Kind Compensatory
Mitigation
The 1990 MOA states "Generally, in-kind compensatory
mitigation is preferable to out-of-kind." This preference for in-kind
compensation is based on the premise that the best way to ensure that
lost aquatic functions are replaced is to compensate for their loss with
the same type of aquatic resource. In-kind compensatory mitigation is
particularly important when the affected aquatic resource is considered
locally important. The ILF Guidance includes a preference for in-kind
mitigation, stating that if a local mitigation bank does not provide in-kind
replacement, an in-lieu-fee arrangement may be used if it would provide
in-kind restoration as mitigation. RGL 02-2 states that in-kind replacement
is generally required when the impacted resource is locally important.
However, current guidance also recognizes that there are
circumstances in which out-of-kind compensatory mitigation may be environmentally
preferable to in-kind mitigation. The 1990 MOA states that acceptable
out-of-kind compensatory mitigation may occur in the use of a mitigation
bank, where it may be environmentally preferable to use mitigation bank
credits to restore a large aquatic resource or a complex of habitats.
The Banking Guidance identifies the advantages of using
out-of-kind compensation at a mitigation bank to address a specific resource
objective, such as the restoration of a particularly vulnerable or valuable
wetland habitat type. Another example of appropriate out-of-kind compensation
noted in the Banking Guidance is when the out-of-kind aquatic habitat
type is determined to have greater ecological value to a particular region
than the affected habitat type. However, the Banking Guidance states that
non-tidal wetlands should typically not be used to compensate for the
loss or degradation of tidal wetlands, or vice-versa. RGL 02-2 also states
that out-of-kind mitigation is appropriate when it is practicable and
provides more environmental or watershed benefits than in-kind compensation.
A watershed-based approach to compensatory mitigation,
as discussed in Section IV.C. of this guidance, would prioritize restoration
efforts, allowing for identification of situations when out-of-kind compensatory
mitigation would be environmentally preferable to in-kind mitigation.
IV. Additional Recommendations and Guidance
A. National Research Council Recommendations
The National Research Council (NRC) addressed the issue
of appropriate use of off-site and out-of-kind compensatory mitigation
in part through recommending a watershed approach to site selection (NRC,
2001; p. 59) (7):
"Site selection for wetland conservation and mitigation
should be conducted on a watershed scale in order to maintain wetland
diversity, connectivity, and appropriate proportions of upland and wetland
systems needed to enhance the long-term stability of the wetland and
riparian systems. Regional watershed evaluation should greatly enhance
the protection of wetlands and/or the creation of wetland corridors
that mimic natural distributions of wetlands in the landscape."
The NRC report also states (pg. 144):
"The committee endorses the watershed approach and
finds the automatic preference for in-kind and on-site compensatory
mitigation...to be inconsistent with that approach."
B. Relationship of This Guidance to Other Mitigation Guidance
Under Development
As part of the Mitigation Action Plan released in December
of 2002, the agencies plan to publish guidance regarding making compensatory
mitigation decisions in a watershed context by 2005. The Watershed Context
Guidance will likely incorporate the recommendations contained in this
Off-Site and Out-of-Kind Compensatory Mitigation Guidance. The agencies
also have developed a model mitigation plan checklist and guidance for
incorporating the NRC Guidelines for Creating and Restoring Self-sustaining
Wetlands into the Clean Water Act Section 404 program, and are developing
standards for mitigation planning and monitoring. These guidance documents
are relevant to mitigation projects in a broad sense, in contrast with
this Off-Site and Out-of-Kind Guidance, which is relevant where one is
considering the appropriateness of site and kind alternatives.
C. Watershed Context
Existing guidance specifies a preference for on-site and
in-kind compensatory mitigation but allows for off-site and/or out-of-kind
mitigation when it is determined to be practicable and environmentally
preferable. The best tool for determining whether off-site or out-of-kind
compensatory mitigation is environmentally preferable is a holistic watershed
plan (8)
incorporating mitigation or restoration priorities. Without such a plan,
there may be many diverging opinions about what is "best" for
a watershed. In the absence of a holistic watershed plan, evaluations
of mitigation options should take into account a wide range of factors
such as: site conditions that favor or hinder success; the needs of sensitive
species; chronic environmental problems such as flooding or poor water
quality; current trends in habitat loss or conversion; current development
trends; and the long-term benefits of available options.
D. Combining Mitigation Types
Decisions on whether to propose or authorize in-kind, out-of-kind,
on-site, or off-site compensatory mitigation need not be either/or decisions.
In some circumstances, a combination of two or more types of mitigation
will provide the best replacement of wetland functions lost to authorized
projects. For example, flood control functions may be best replaced on-site,
whereas habitat for species sensitive to human presence may be best replaced
off-site. Similarly, the best way to provide habitat for locally important
animal species may be to replace lost habitat with a combination of habitats,
some of which would be in-kind replacement, but others that would be out-of-kind
habitats. As with any mitigation proposal, but especially when mitigation
is split between two or more sites, it is essential to provide sufficient
information to demonstrate the ecological benefits of the proposal.
E. Off-site Mitigation
If off-site mitigation is consistent with or supported
by a holistic watershed plan, then it is considered acceptable. If it
is not, other considerations for determining if off-site mitigation is
environmentally preferable include, but are not limited to the following:
- On-site conditions do not favor successful establishment
of the required vegetation type, or lack the proper soil conditions,
or hydrology.
- On-site compensation would result in an aquatic habitat
that is isolated from other natural habitats or severely impaired by
the effects of adjacent development.
- Off-site location is crucial to one or more species
that is threatened, endangered, or otherwise of concern, and the on-site
location is not.
- Off-site location is crucial to larger ecosystem functions,
such as providing corridors between habitats, and the on-site location
is not.
- Off-site compensation has a greater likelihood of success
or will provide greater functional benefits.
When determining whether off-site mitigation is environmentally
preferable, the value of the site-specific functions at the project site,
such as flood control, nutrient retention, sediment filtering, and rare
or unique habitats or species, should be fully considered. When conditions
do not favor on-site compensation, off-site compensatory mitigation should
be located as close to the impact site as possible, while still replacing
lost functions. Preference should be given to off-site options within
the same hydrologic unit (e.g., based on the 8-digit U.S. Geological Survey
Hydrologic Unit Code or appropriate substitute) or ecoregion as the impact
site.
F. Out-of-kind Mitigation
If out-of-kind mitigation is consistent with or supported
by a holistic watershed plan, then it is considered acceptable. If it
is not, other considerations for determining if out-of-kind mitigation
is environmentally preferable include, but are not limited to the following:
- In-kind compensation would result in undesirable
aquatic habitat type, such as one that is dominated by non-native invasive
species.
- In-kind compensation is extremely difficult to do successfully.
- Out-of-kind compensation is crucial for protecting or
replacing important functions specific to a particular wetland or other
particular aquatic habitat type, and in-kind compensation is not. Such
function might include habitat for a species that is threatened, endangered,
or otherwise of concern; or a water quality function that is best performed
by one type of aquatic habitat.
- Out-of-kind compensation is necessary to prevent the
decline of a habitat type that is rare or becoming scarce, and in-kind
compensation is not.
- Out-of-kind compensation will provide or protect scarce
functions to replace common or readily available functions.
- Out-of-kind compensation has a greater likelihood of
success or will provide greater functional benefits.
G. Characteristics of Successful Compensatory Mitigation
Projects
Whether compensatory mitigation is on-site, off-site, in-kind,
or out-of-kind, a number of characteristics are generally associated with
successful compensatory mitigation proposals. These characteristics should
be considered when designing or evaluating mitigation projects.
The mitigation project should:
- Be sustainable in the context of adjacent land
uses. Although urban or suburban mitigation sites are often considered
unsuitable because of adjacent land uses, such a determination should
not be made until after the site is evaluated for vulnerability to pollutants,
disturbance, and other impacts from uses associated with adjacent land
parcels. Considerations such as appropriate buffers and site restriction
mechanisms may need to be incorporated to expect reasonable success
for projects in these more vulnerable areas.
- Be sustainable in the context of natural processes,
particularly with respect to hydrology. The aquatic habitat at the compensation
site should mimic natural processes and landscape position.
- Have little or no adverse impacts on the environment.
- Include good stewardship and long-term protection provisions
(e.g., financial assurances, site protection mechanisms, monitoring
and contingency provisions, etc.).
- Have clear goals, with specifically defined measurable
performance standards, in order to improve mitigation effectiveness.
Performance standards in permits should reflect mitigation goals and
be written in such a way that ecological viability can be measured and
the impacted functions replaced.
V. General
A. Current Food Security Act (FSA) legislation (also known
as "Swampbuster") limits the extent to which mitigation can
be used for FSA purposes. Notwithstanding anything in this guidance, if
a mitigation proposal is to be used for FSA purposes, it must meet the
requirements of FSA.
This guidance does not alter or modify requirements of
any Federal law or regulation, or modify any prior guidance. The signatory
agencies will employ this guidance in concert with the 1990 MOA between
the EPA and the Corps, the 1995 Federal Guidance on Mitigation Banking,
the 2000 Federal Guidance on In-Lieu-Fee Arrangements, and the 2002 Corps
RGL on Compensatory Mitigation Projects.
B. The statutory provisions and regulations mentioned in
this document contain legally binding requirements. However, this guidance
does not substitute for those provisions or regulations, nor is it a regulation
itself. This guidance does not impose legally binding requirements on
the signatory agencies or any other party, and may not apply to a particular
situation in certain circumstances. The signatory agencies retain the
discretion to adopt approaches on a case-by-case basis that differ from
this guidance when they determine that it is appropriate to do so. Such
decisions will be based on the facts of a particular case and applicable
legal requirements. Therefore, interested parties are free to raise questions
and objections about the substance of this guidance and the appropriateness
of its application to a particular situation.
C. This guidance does not and is not intended to alter
any provisions of applicable state law or regulations. It is the responsibility
of the applicant to comply with all applicable state laws and regulations.
D. As of the date of the last signature below, the agencies
will take this guidance into account in their evaluation of compensatory
mitigation proposals.
E. This guidance is based on evolving information and may
be revised periodically without public notice. The signatory agencies
welcome public comments on this guidance at any time and will consider
those comments in any future revision of this guidance.
For Further Information Contact: Ms. Katherine Trott (Corps)
at (202) 761-5542; Mr. Palmer Hough (EPA) at (202) 566-1374; Ms. Jeanette
Gallihugh (USFWS) at (703) 358-2183; Ms. Susan Marie Stedman (NMFS) at
(301) 713-4300; Mr. Albert Cerna (NRCS) at (202) 690-3501; and Mr. Fred
Bank (FHWA) at (202) 366-5004.
________________________________________
George S. Dunlop Date
Deputy Assistant Secretary of the Army
(Policy and Legislation)
Department of Army
________________________________________
Benjamin H. Grumbles Date
Acting Assistant Administrator for Water
U.S. Environmental Protections Agency
________________________________________
Steven Williams Date
Director
Fish and Wildlife Service
Department of Interior
________________________________________
Bruce I. Knight Date
Chief
Natural Resources Conservation Service
Department of Agriculture
________________________________________
William T. Hogarth, Ph.D. Date
Assistant Administrator for Fisheries
National Oceanic and Atmospheric
Administration, Department of Commerce
________________________________________
Tyler Duvall Date
Deputy Assistant Secretary for
Transportation Policy
Department of Transportation
Top |